The order of connection to engineering infrastructure is regulated by the Law of the Republic of Kazakhstan No. 242-II of 16 July 2001 «Architecture, Town Planning and Construction Activity in the Republic of Kazakhstan», Order No. 750 of the Minister of National Economy of the Republic of Kazakhstan of November 30, 2015 «Approval of the Organization Rules building and the passage of licensing procedures in the construction industry «(Building Regulations) and other normative legal acts in the field of architectural, town-planning and construction activities.
According to paragraph 18 of Article 1 of the law, the engineering infrastructure is a set of enterprises (organizations), objects (buildings and structures), communications and utilities, creating normal conditions for people's livelihoods, and the sustainable operation of production or circulation of goods and services.
In accordance with the Building Regulations, the implementation of any construction project is carried out on the basis of the relevant right to the land plot and the following stages:
Source materials for the development of construction projects include:
The application for the provision of APTand technical specifications is submitted in accordance with Annex 1 to the Building Regulations to the structural subdivision of the local executive body (LEB) that performs functions in the field of architecture and town planning through the web portal of «e-government» or the State Corporation with the attachment:
The LEB, which carries out functions in the field of architecture and urban planning, sends to the providers of engineering and utility services a questionnaire for obtaining technical specifications.
Providers of engineering and utilities services within 5 (five working days) from the date of reception of the questionnaire and topographical survey prepare and send to the structural subdivision of the LEB carrying out functions in the field of architecture and town planning technical conditions with a preliminary scheme of routes of external engineering networks.
The structural subdivision of the LEB, which performs functions in the field of architecture and town planning, in the case of compliance of the planned construction with the approved detailed design project, prepares the following materials:
Materials and documents prepared by the structural subdivision of the LEB that performs functions in the field of architecture and town planning are sent to the State Corporation or placed on the web portal of «electronic government».
The technical conditions must contain complete information about the schemes for connecting the object to communications, and the works that must be performed for successful connection. They determine the connection points, the conditions of delivery and the size of the allocated capacities, specify measures for accounting and saving of consumed resources. In addition, the necessary environmental standards are included in the technical specifications.
1. Connection to public networks of water supply and sewage:
pressure in water supply pipelines; at the requirement of Technical conditions (TC) about checking of the existing network on the flow pass — the scheme of networks with the indication of the connected objects.
2. Heat supply:
3. Electric power supply:
4. Gas supply:
5. Telephone Installation:
6. Radiocommunications:
7. Television:
Obtaining and agreeing technical specifications can take a long time, because each part is formalized in the appropriate authority.
In addition, if the proposed communication route passes through land plots that do not belong to the customer, it will be necessary to agree separately with the owners of each of them.
Documents are prepared for free. You can find out the detailed requirements for obtaining specifications in the architecture management, as well as with service providers in your village.
After this procedure, you should order engineering network projects. Gas supply and electricity supply will require separate documents, for water supply and sewerage — one common.
Next, you need to approve them with service providers and in the architecture administration and you can proceed with the laying of communications, the insert to the backbone networks.